Construction of facilities for new buildings at the BH FLORENCE plant.
ELLEGI S.P.A.
Client Cern
Scope of work EPC contract for mechanical installation, E&I and LHC equipment
Resources 92
Technical details Creation of the cooling system, installation of heat exchangers, cooling towers, centrifugal pumps and expansion vessels.
3800 valves and 55 km of cable were installed.
Total hours worked: 500,000